Shabwa Solar Power Station (53 MW) officially begins operation, while work starts on the second phase of Aden’s solar project (120 MW) with UAE support.

REPORTS - منذ 7 ساعات

South Eye | South24

The ceremony was attended by UAE Ambassador to Yemen Mohammed Hamad Al-Zaabi, Yemen's Minister of Electricity, the Governor of Shabwa, and other local officials.

The plant, located northwest of Ataq city, was built on a 600,000-square-meter site and comprises more than 85,000 solar panels, 159 electrical inverters, a night storage system, six subsidiary conversion stations, and a 15-kilometer transmission line supported by 51 towers linking it to the main grid. 

فيديو